May 1 - May 15
Pew Installation
Wood Trim
Glass Balcony Railing
Basement Ceiling Tile
Fire Alarm
Altar Furniture
Flooring
Doors and Hardware
April 12 - April 30
Lighting Controls
Sound System
Flooring in Nave and Sactuary
Wood Trim Throughout
Ceiling Tile Grid in Basement
Front Steps
New Organ Installation
Old Sacristy Cabinet Reinstalled (refinished)
April 1 - April 11
Bathroom Tile Installation
Interior Door Install
Decorative Painting final touches and touchup
Front Steps Installation
Basement Lift Installation
Narthex Wall Hardwood Finishes
Continued Electrical/HVAC/Audio/Fire Alarm Systems Install
Choir Loft and Sacristy Flooring Install
March 18 - March 31
“Adeamus ergo cum fiducia ad thronum gratiae”
(Let us go therefore with confidence to the throne of grace) - Hebrews 4:16a.
Decorative Painting on Ceiling and Walls Continues
Painting and Casework Installation
Scaffold Removal!!!
Tile Installation in Basement Bathrooms
Front Steps Removed for replacement due to poor condition
March 4 - March 17
Decorative Painting on Ceiling continues
Installation of Wood Door Frames and other Millwork
Drywall finishes on First Floor
Front Step Replacement Demolition
March 1 - March 3
Decorative Painting on Ceiling continues
Plaster Repairs in Sacristies
Continued install of Electrical and Life Saftey Systems (fire alarm, emergency lighting)
February 23 - March 1
Decorative Painting on Ceiling continues
Basement Painting
Installation of Cabinets in Basement
Installation of new exterior Doors in basement
Continued install of Electrical and Life Saftey Systems (fire alarm, emergency lighting)
Install of new Belltower access door and suppor structure for Organ Speakers
Lighting Capital construction
Repair to plaster in sacristies to prepare for painting
February 3 - February 17
Decorative Painting on Ceiling continues
Painting of Door frames and walls in basement
Continued install of Electrical and Life Saftey Systems (fire alarm, emergency lighting)
Install of new Belltower access door and suppor structure for Organ Speakers
Lighting Capital construction
Repair to plaster in sacristies to prepare for painting
Visit and inspection of Altar Furniture construction progress
January 30 - February 3
Re-Mobilize workforces to make repairs and to finish painting
Painting in Basement
Electrial Systems, interior and exterior
Rebuilding of Bell-Tower Access and New Organ Speaker Support Structure
HVAC Installation - Condenser Hook-up, Control Wiring, Insulation
January
Work on Electrial Systems, interior and exterior.
Investigate and Come up to solution to paint problems.
Finish drywall in Basement, prepare for painting.
Walkthrough of ceiling with members of rebuild committee to review repairs and identify areas to "touch up" before final painting.
December 9 - December 28
Electrical Panel Installation and Permanent Power Install Throughout Building
HVAC Installation
Drywall Taping/Mudding in Basement, Narthex and first floor rooms
November 26 - December 9
Electrical Panel Installation and Permanent Power Install Throughout Building
HVAC Installation
Drywall Taping/Mudding in the Basement
Attic Insulation Install
November 15 - November 25
Electrical Panel Installation and Permanent Power Install
HVAC Installation
Drywall Taping/Mudding in the Basement
November 1 - November 14
Decorative Ceiling Painting Continues
Electrical Panel Installation and Permanent Power Install
HVAC Installation
Tempoary Heat
October 26 - October 31
Decorative Ceiling Painting Continues
Electrical Panel Installation and Permanent Power and Meter Install
HVAC Control Installation
Drywall Installation
October 15 - October 25
Base Coat Painting
Basement Drywall Installation
Electrical Panel Installation
Heating Piping and Insulation
Decorative Ceiling Painting
Belltower Bell Frame Installation
October 8 - October 14
Plaster Repair and Wall Skim coating continuing
Base Coat Painting
In-wall inspections/attic inspections
M/E/P systems installation
Ceiling Painting Mock-Up (finish painting to start next week!!)
October 1 - October 7
Plaster Repair in Sanctuary and skim coating
Base Coat painting of ceiling and sanctuary
September 20 - September 30
Installation of HVAC Systems (Blowers, duct, piping, plumbing)
Plaster Repair in Sanctuary and skim coating
Installation of Electrical Systems
September 1 - September 20
Installation of Electrical Systems (Above Ceiling)
Installation of HVAC Systems
Plaster Repair in Sanctuary and skim coating
Drywall Installation in basement
August 20 - August 31
Installation of Electrical Systems (Above Ceiling)
Installation of HVAC Systems
Installation of basement windows
August 14 - August 19
Rough Carpentry Completed
Installation of HVAC Systems
Installation of Electrical and Fire Alarm Systems
August 7 - August 13
Installation of HVAC Systems
Installation of Electrical and Fire Alarm Systems
Installation of Attic Catwalk and Saftey Systems
August 1 - August 6
Scaffolding Installed
Continued Installation of HVAC System
Boilers and Air Handlers Delivered
July 16 - July 31
Continued Installation of Wiring
Installation of outdoor air conditioning condensing units
Installation of framing on first floor for gathering space and balcony
Installation of scaffolding
Week of July 9 -15
Removal of Old Organ
Removal of Old Bell hardware for replacment
Installation subfloor in choir loft
Insulation of ductwork in basement
Continued Installtion of Electrical and Mechanical Systems
Installation of Plumbing for Bathrooms
Week of July 2 - 8
Installation of Basement Stairwell
Installation of Ductowork througout
Installation of Wiring and Piping for HVAC Units
Completion of subfloor in Nave
Week of June 27 - July 1
Installation of Basement Stairwell
Demolition of balcony facade
Installation of Ductowork througout
Installation of Wiring for HVAC Units
Installation of new underground conduit to Utility Pole in Right of Way
Weeks of June 12 - 24
Continued Installation of Electrical Systems Wiring
Continued Installation of Sub-Floor Decking
Work to support existing stairwell after discovering structual concerns
Demolition of balcony for reuse in put back
Installation of Ductwork throughout
Installation of Heating Piping for new HVAC Units
"New" Stations from a closed church arrive
Week of June 4 - June 11
Continued Basement Framing of Interior Walls - Bathrooms, Kitchen
Continued Installation of Electrical Wiring
Continued Installation of Floor Decking
Installation of Sactuary Steps
Trenching and Installation of underground conduit for electrical service from pole
Week of May 28 - June 3
Continued Basement Framing of Interior Walls
Installation of Electrical Wiring and Panels
Continued Installation of Floor Decking
Week of May 21 - 27
Plumbing Trenches Poured with Concrete
Main Floor Decking begun.
Basment interior wall framing begun.
New electrical installation begun.
Week of May 14 - 20
Floor Joists installation begun.
Main Nave flooring installation begun.
Broken sewer line to sanitary manhole repaired and trenches prepped for concrete.
Week of May 7 - 13
Steel Columns and Floor Beams installed.
Concrete foundation poured for elevator lift pad.
Floor joist hangers installed and engineered floor joists delivered to site.
Rebuild Committee met to discuss decorative painting design with representative from Conrad Schmitt Studios as well as other updates from architect.
Week of May 2 - 6
Chimney Demolition Complete and Roof and Trim Work Completed to prevent future leaks.
Strip footings formed, rebar and anchor bolts place and concred foundations poured.
Underslab plumbing and electrical run.
April 24, 2022
All are welcome to join us after 8:30 Mass on Sunday, April 24th at the Sacred Heart Church Fulcher Center for the kick-off of our Restore & Grow Campaign. Coffee, Juice and Doughnuts will be available.
We will also have a special “ground breaking” ceremony inaugurating our re-building as well as tours of the church building.
April 16, 2022
Restore & Grow mailings have been sent out to all parishioners and bulletin and Flocknote announcment made for April 24th Campaign Kick-Off!
March 25, 2022
Our insurance company approves design and budget to release project for construction
March 1, 2022
Diocese gives approval for $500,000 fundraising campaign based on strong Sacred Heart financials and once in a generation opportunity to Restore & Grow for the future